Skip to content
LeeterWire · fasteners · site hardware
Leeter tools · AI-assisted planning

Slab reinforcement estimator

Enter a slab and get the rebar, tie wire, chairs and mesh it needs — the accessories most calculators leave out. A planning estimate for ordering, not a structural design.

Ask Leeter AI ↓
Bar spacing (mm, both ways)
Bar size
Mats
Estimated materials
244kg

12 mm rebar (52 bars/mat)

2.2kg

tie wire · ≈2 coils (3.5 lb)

35

chairs @ 1 m grid

2

mesh sheets (if using mesh instead)

Planning estimate, not a structural design. Bar count is a simple grid (dimension ÷ spacing + 1); it ignores laps, edge bars, cover and development length, which your engineer sets. Tie wire assumes every intersection tied (≈0.2 m of 16 ga per tie); mesh option assumes 6×2.4 m sheets at ~12 m² effective after laps. Use it to order, then confirm against the drawings.

How this is calculated

  1. 1
    Model

    The tool lays out an orthogonal two-way bar grid. In each direction the number of bars is the span divided by the on-centre spacing plus one (the “fence-post” rule — a run of length D at spacing s needs D/s gaps but D/s+1 bars): n_x = floor(W/s)+1 and n_y = floor(L/s)+1. Total steel length = (n_x·L + n_y·W) × mats.

  2. 2
    Weight

    Bar weight = total length × the standard unit mass. Metric bars follow the exact rule w = D²/162 ≈ 0.006165·D² kg/m (the mass of a round steel section at 7,850 kg/m³): 8 mm 0.395, 10 0.617, 12 0.888, 16 1.578, 20 2.466, 25 3.853 kg/m. Imperial bars use the ASTM A615 nominal mass (#3 0.560, #4 0.994, #5 1.552, #6 2.235 kg/m).

  3. 3
    Tie wire, chairs and mesh

    Tie wire = number of bar crossings (n_x·n_y·mats) × ~0.2 m of 16-gauge wire per tie (16 ga = 1.588 mm = 0.01555 kg/m), converted to 3.5 lb (≈1.6 kg) coils. Chairs = (L/grid+1)×(W/grid+1), about one per m² at a 1 m grid. The mesh alternative = slab area ÷ ~12 m² effective coverage per 6.0×2.4 m sheet (14.4 m² gross minus one 300 mm lap each way).

  4. 4
    Waste

    Bars ship in fixed stock lengths and any long span needs lap splices (~40–50× bar diameter), so a waste/lap allowance (default 10%) is applied to both the steel and the tie-wire figures — this is the single factor most take-offs omit and the only place an estimate can under-order.

  5. 5
    Worked example

    A 6×4 m slab at 200 mm both ways, 12 mm bar, single mat: n_x = floor(4/0.2)+1 = 21, n_y = floor(6/0.2)+1 = 31; length = 21×6 + 31×4 = 250 m; weight = 250×0.888 = 222 kg, ×1.10 waste ≈ 244 kg. Crossings = 21×31 = 651, tie wire ≈ 651×0.2×0.01555×1.10 ≈ 2.2 kg (≈ 2 coils).

  6. 6
    Assumptions & limits

    Bars are assumed to run at the nominal spacing and every intersection tied (an upper bound — crews often tie a ~50–60% checkerboard). This is a material take-off, not a structural design: bar size, spacing, cover, laps and development length must come from the engineer’s design to ACI 318 / Eurocode 2.

Diagram: how the Slab reinforcement estimator is calculated
Bars run both ways at the on-centre spacing; each crossing is a tie point (n_x × n_y intersections).

Leeter provides the tool, not a warranty of the result. Every figure above is a planning estimate for reference only — confirm structural, code and customs decisions with your engineer, inspector or broker.

Leeter AIAsk about your project · powered by leeter.cn
⌘/Ctrl + Enter

From estimate to firm quote

These tools size the job. Send us the spec and we'll price the material, packing and lead time.

Answer-first toolsevery calculation shown
Leeter AItrained on the specs & standards
Manufacturer pricingFOB or CIF, packed for you